Turner Page Music Ltd v Torres Design Associates Ltd

Language: English Series: Construction Industry Law Letter ; [1997] CILL1263-1268(6)Publication details: 1997Subject(s): Summary: ORD 12 march 1997. P engaged D to provide design and professional services in connection with the redevelopment of a cinema. Contract prices agreed were £467,140 (later £450,000) for the building works and a separate contract for M&E work. Following completion, which was a week after the contractual date, D issued final certificate and final cost of £827,000 including M&E work. P was by then in financial difficulties and after negotiations sold the theatre to a third party. P sued, claiming a number of breaches of duty on behalf of D in the performance of various professional duties. P`s action allowed. TAKEN FROM JOURNAL ABSTRACT
Holdings
Item type Current library Call number Copy number Status Barcode
Law report London Journal article X85186 (Browse shelf(Opens below)) 1 Available 79599-1001

ORD 12 march 1997. P engaged D to provide design and professional services in connection with the redevelopment of a cinema. Contract prices agreed were £467,140 (later £450,000) for the building works and a separate contract for M&E work. Following completion, which was a week after the contractual date, D issued final certificate and final cost of £827,000 including M&E work. P was by then in financial difficulties and after negotiations sold the theatre to a third party. P sued, claiming a number of breaches of duty on behalf of D in the performance of various professional duties. P`s action allowed. TAKEN FROM JOURNAL ABSTRACT