Determination of completion date

Language: English Series: EGCS ; 1990 87Publication details: 1990Subject(s): Summary: Rosehaugh Stanhope (Broadgate Phase 6) plc and another v Redpath Dorman Long Ltd CA 26 June 1990. The appeal was allowed that with the contractor `s denial of the breach of contractual obligation to complete by specified dates and the construction manager`s inability to prove this, the construction manager `s determination of damage liability is not binding.

Rosehaugh Stanhope (Broadgate Phase 6) plc and another v Redpath Dorman Long Ltd CA 26 June 1990. The appeal was allowed that with the contractor `s denial of the breach of contractual obligation to complete by specified dates and the construction manager`s inability to prove this, the construction manager `s determination of damage liability is not binding.