The effects of adjudication.

By: Series: Contract Journal ; 399(6232) 30 June 1999, 22(1)Publication details: 1999Subject(s): Summary: Considers the effect of an interim assessment by an adjudicator on subsequent assessments, and the case " Odebrecht Oil and Gas v North Sea Production Company" which dealt with the issue. Concludes that parties are not usually entitled to a re-adjudication of rights and obligations following an adjudication, although an adjudicator can take all relevant issues freshly into account in later interim assessments.

Considers the effect of an interim assessment by an adjudicator on subsequent assessments, and the case " Odebrecht Oil and Gas v North Sea Production Company" which dealt with the issue. Concludes that parties are not usually entitled to a re-adjudication of rights and obligations following an adjudication, although an adjudicator can take all relevant issues freshly into account in later interim assessments.