Synchronise watches

By: Series: Building ; 266(8207) 23 November 2001, 50-51(2)Publication details: 2001Subject(s): Summary: Discusses the case "Sindall Ltd v Solland" which deals with two key issues. Sindall failed to give contract administrator Michael Edwards & Associates (MEA) enough time to respond to its complaint before starting adjudication which meant the first adjudicator had no right to adjudicate; MEA accused Sindall of not proceeding reasonably and diligently yet failed to give Sindall the correct extension of time which meant MEA had no grounds for giving notice.
Holdings
Item type Current library Call number Copy number Status Barcode
Journal article London Journal article ABS64851 (Browse shelf(Opens below)) 1 Available 115977-1001

Discusses the case "Sindall Ltd v Solland" which deals with two key issues. Sindall failed to give contract administrator Michael Edwards & Associates (MEA) enough time to respond to its complaint before starting adjudication which meant the first adjudicator had no right to adjudicate; MEA accused Sindall of not proceeding reasonably and diligently yet failed to give Sindall the correct extension of time which meant MEA had no grounds for giving notice.