Series: Construction Law Journal ; [2002] Const L J 49-55(7)Publication details: 2002Subject(s): Summary: QBD 18 February 2000 Defendant (C) was main contractor on project with claimant (A). Work began January 1998 pursuent to letter of intent dated 18 December 1997. 3 April 1998 DOM/1 signed by each party. C contended contract entered into that day. A contended contract undated, and contract not entered into until after 1 May 1998. C referrred claim to adjudication under HGCRA. Decision dated 14 January 2000 found for C against A. A sought enforcement. C contended contract entered into 3 April 1998, and challenged adjudicators jurisdiction. "Held" that contract between parties took effect from 12 April 1999 and was not a variation of the earlier letter of intent.
Holdings
Item type Current library Call number Copy number Status Barcode
Law report London Journal article ABS65366 (Browse shelf(Opens below)) 1 Available 117893-1001

QBD 18 February 2000 Defendant (C) was main contractor on project with claimant (A). Work began January 1998 pursuent to letter of intent dated 18 December 1997. 3 April 1998 DOM/1 signed by each party. C contended contract entered into that day. A contended contract undated, and contract not entered into until after 1 May 1998. C referrred claim to adjudication under HGCRA. Decision dated 14 January 2000 found for C against A. A sought enforcement. C contended contract entered into 3 April 1998, and challenged adjudicators jurisdiction. "Held" that contract between parties took effect from 12 April 1999 and was not a variation of the earlier letter of intent.