Carillion Construction Ltd v Devonport Royal Dockyard
Series: Building Law Reports ; [2003] 2 BLR 79-88(10)Publication details: 2003Subject(s):- CARILLION CONSTRUCTION LTD V DEVONPORT ROYAL DOCKYARD LTD
- -DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION-ADJUDICATORS-ADJUDICATORS' JURISDICTION
- CONSTRUCTION DISPUTES
- CONTRACTS IN WRITING
- ORAL CONTRACTS
- R J T CONSULTING ENGINEERS LTD V D M ENGINEERING (NI) LTD
- MANGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION
| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Law report | London Journal article | ABS66599 (Browse shelf(Opens below)) | 1 | Available | 122176-1001 |
TCC 27 November 2002. Claimant (C)'s application for summary judgment to enforce adjudicator's decision was dismissed. An oral agreement varying terms of a contract did not form part of a written contract and therefore the Housing Grants, Construction and Regeneration Act 1996 s107 did not apply. "R J T Consulting v D M Engineering" (CA X118297) applied. There was no dispute to refer to adjudication as C had failed to provide clarification of its claim as requested by defendant (D).