What might have been

By: Language: English Series: Building ; 260(7887) 7 April 1995, 33(1)Publication details: 1995Subject(s): Summary: A reminder that in a loss and expense claim following overrunning, a contractor must be able to show that the delay prevented new work being undertaken, that work was indeed available and that the tender would have been won.