Synchronise watches

By: Series: Building ; 266(8207) 23 November 2001, 50-51(2)Publication details: 2001Subject(s): Summary: Discusses the case "Sindall Ltd v Solland" which deals with two key issues. Sindall failed to give contract administrator Michael Edwards & Associates (MEA) enough time to respond to its complaint before starting adjudication which meant the first adjudicator had no right to adjudicate; MEA accused Sindall of not proceeding reasonably and diligently yet failed to give Sindall the correct extension of time which meant MEA had no grounds for giving notice.

Discusses the case "Sindall Ltd v Solland" which deals with two key issues. Sindall failed to give contract administrator Michael Edwards & Associates (MEA) enough time to respond to its complaint before starting adjudication which meant the first adjudicator had no right to adjudicate; MEA accused Sindall of not proceeding reasonably and diligently yet failed to give Sindall the correct extension of time which meant MEA had no grounds for giving notice.